ORIGINAL ARTICLE
The Effects of Delays in Algerian Construction Projects: An Empirical Study
 
More details
Hide details
1
Department of Civil Engineering, LMGHU Laboratory, University 20 aout 1955-Skikda, Algeria
 
 
Online publication date: 2021-06-28
 
 
Publication date: 2021-06-01
 
 
Civil and Environmental Engineering Reports 2021;31(2):218-254
 
KEYWORDS
ABSTRACT
This paper examines the effects of delays in the Algerian construction industry in order to identify the various critical aspects of the causes for improving the economy in the construction sector. A questionnaire survey was conducted to assess the perceptions of all players in the construction industry, which led to the identification of the most significant impacts of delays. The results show that ten main effects of delays in the construction sector are at the origin of many constraints that have a negative impact on the economy of the country. Further, the factor analysis technique was performed to categorize the identified effects into main groups, and it yielded 5 groups (factors). As an important contribution, the relationship between these groups was tested using the SMART-PLS, and a structural model has been developed. Also, a comparative study with other previous works on the most critical effect of delays in construction projects has been conducted and the results show that the main effects of delays in the construction industry are at the root of many constraints in reaching and achieving the objectives.
REFERENCES (47)
1.
Abdullah, MR, Abdul Azis, AA and Abdul Rahman, I 2009. Potential Effects on Large Mara Construction Projects Due To Construction Delay. International Journal of Integrated Engineering (IJIE) 1, 53–62.
 
2.
Ahmed, SM, Azhar, S, Castillo, M and Kappagantula, P 2002. Construction Delays in Florida: An Empirical Study. Final Report. Florida International University:, no. August. Dept. of Community Affairs, Miami.
 
3.
Aibinu, AA and Jagboro, GO 2002. The Effects of Construction Delays on Project Delivery in Nigerian Construction Industry. International Journal of Project Management 20, 593–99.
 
4.
Alagidede, P and Jones O, M 2018. Construction, Institutions and Economic Growth in Sub-Saharan Africa. ERSA Working Pape 10, 136–63.
 
5.
Alavifar, AH and Shadab M 2014. Identification, Evaluation and Classification of Time Delay Risks of Construction Project in Iran. International Conference on Industrial Proceedings of the 2014 International Conference on Industrial Engineering and Operations Management Bali, Indonesia, January 7 – 9, 219-229.
 
6.
Amoatey, CT, Yaa AA, Ebenezer, A and Samuel, F 2015. Analysing Delay Causes and Effects in Ghanaian State Housing Construction Projects. International Journal of Managing Projects in Business 8, 198–214.
 
7.
Assaf, SA and Al-Hejji, S 2006. Causes of Delay in Large Construction Projects. International Journal of Project Management 24, 349–57.
 
8.
Bajjou, MS and Chafi, A 2020. Empirical Study of Schedule Delay in Moroccan Construction Projects. International Journal of Construction Management 20, 783–800.
 
9.
Chiang, YH, Li, T and Francis KWW 2015. Causal Relationship between Construction Activities, Employment and GDP: The Case of Hong Kong. Habitat International 46, 1–12.
 
10.
Dixit, S, Pandey, AK, Mandal, SN and Bansal, S 2017. A Study of Enabling Factors Affecting Construction Productivity: Indian Scnerio. International Journal of Civil Engineering & Technology 8, 741–58.
 
11.
Dlamini, M and Cumberlege, R 2021. The Impact of Cost Overruns and Delays in the Construction Business. IOP Conference Series: Earth and Environmental Science 654, 012029.
 
12.
Durdyev, S, Maksat, O and Syuhaida, I 2017. Causes of Delay in Residential Construction Projects in Cambodia. Cogent Engineering 4, 1–12.
 
13.
Ojoko, EO, Tanko, BL, Ojoko, O and Enegbuma, WL 2016. Project Delay Causes And Effects In The Construction Construction Industry. IGCESH2016, University of Technology Malaysia, Johor Bahru, Malaysia, August, 15-17, 1–12.
 
14.
Field, A 2013. Discovering Statistics Using IBM SPSS Statistics. London. (UK): Publisher. SAGE Publications Ltd. 4th ed.
 
15.
Frimpong, Y, Oluwoye, J and Crawford, L 2003. Causes of Delay and Cost Overruns in Construction of Groundwater Projects in a Developing Countries; Ghana as a Case Study. International Journal of Project Management 21, 321–26.
 
16.
Gashahun, AD 2020. Causes and Effects of Delay on African Construction Projects: A State of the Art Review. Civil and Environmental Research 12, 41–53.
 
17.
Gbahabo, PT and Ajuwon, OS 2017. Effects of Project Cost Overruns and Schedule Delays in Sub-Saharan Africa. European Journal of Interdisciplinary Studies 7, 46.
 
18.
Gebrehiwet, T and Luo, H 2017. Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study. Procedia Engineering 196, 366–74.
 
19.
Hair, JF, Jeffrey, JR, Marko, S and Christian, MR 2018. Article Information : When to Use and How to Report the Results of PLS-SEM. European Business Review 31, 2–24.
 
20.
Haq, S, Rahsid, Y and Aslam, MS 2014. Causes of Delay in Construction Projects of Punjab-Pakistan : An Empirical Study.” Journal of Basic and Applied Scientific Research 4, 98–104.
 
21.
Henseler, J 2018. Partial Least Squares Path Modeling: Quo Vadis? Quality and Quantity 52, 1–8.
 
22.
Henseler, J, Christian, MR and Marko, S 2015. A New Criterion for Assessing Discriminant Validity in Variance-Based Structural Equation Modeling. Journal of the Academy of Marketing Science 43, 115–35.
 
23.
Kamalan, H, 2020. Root Cause Analysis of Delays in Dam Construction (Case Studies : Karun-3, Marun, Shafaroud and Jamishan Dams) Journal of Hydraulic Structures 6, 45–58.
 
24.
Khair, K, Hazir, F, Zainai, M and Mohammad, R 2016. Causes and Effects of Delay Factors in Road Construction Projects in Sudan. International Journal of Applied Engineering Research 11, 9526–33.
 
25.
Kikwasi, G 2012. Causes and Effects of Delays and Disruptions in Construction Projects in Tanzania. Australasian Journal of Construction Economics and Building - Conference Series 1, 52-59.
 
26.
Kuşakcı, AO, Berk, A and Emir, B 2017. An Analysis of Causes and Effects of Delays in Construction Projects in Libyan Oil Industry. Karaelmas Fen ve Mühendislik Dergisi 7, 274–82.
 
27.
Mahamid, I 2017. Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects. International Journal of Architecture, Engineering and Construction 6, 51-58.
 
28.
Mukuka, M, Aigbavboa, C and Thwala,W 2015. Effects of Construction Projects Schedule Overruns: A Case of the Gauteng Province, South Africa. Procedia Manufacturing 3, 1690–95.
 
29.
Ngacho, C and Das, D 2014. A Performance Evaluation Framework of Development Projects: An Empirical Study of Constituency Development Fund (CDF) Construction Projects in Kenya. International Journal of Project Management 32, 492–507.
 
30.
Niazai, GA and Gidado, K 2012. Causes of Project Delay in the Construction Industry in Afghanistan. Proceedings of EPPM 2012 International Conference on Engineering, Project and Production Management. United Kingdom University of Brighton, September, 10-11, 63-74.
 
31.
Nyoni, T 2018. An Empirical Assessment of Causes & Effects of Delay in Residential Construction Projects In. International Journal of Advances in Engineering & Scientifc Research 5, 34–46.
 
32.
Obodoh, D 2016. Causes and Effects of Construction Project Delays in Nigerian Construction Industry. International Journal of Innovative Science, Engineering & Technology 3, 65–84.
 
33.
Oladinrin, TO, Ogunsemi, DR and Aje, IO 2012. Role of Construction Sector in Economic Growth: Empirical Evidence from Nigeria. FUTY Journal of the Environment 7, 50–60.
 
34.
Oshungade, OO and Kruger, D 2017. A Comparative Study of Causes and Effects of Project Delays and Disruptions in Construction Projects in the South African Construction Industry. Journal of Construction Engineering and Project Management 7, 13–25.
 
35.
Owalabi, JD et al. 2014. Causes and Effects of Delay on Project Construction Delivery Time. International Journal of Education and Research 2, 197–208.
 
36.
Rachid, Z, Boudouh, T and Baheddi, M 2019. Causes of Schedule Delays in Construction Projects in Algeria. International Journal of Construction Management 19, 371–81.
 
37.
Rashid, Y 2020. Analysis of Delay Factors and Their Effects on Construction Projects. Management Science Letters 10, 1197–1204.
 
38.
Salah, A and Ahmed, M 2018. Causes and Effect of Delay on Construction Project Delivery Time in Somalia : Hanad Construction & General Trading Company Case Study.
 
39.
Sambasivan, M and Soon, YW 2007. Causes and Effects of Delays in Malaysian Construction Industry. International Journal of Project Management 25, 517–26.
 
40.
Santos, J and Reynaldo, A 1999. Cronbach’s Alpha: A Tool for Assessing the Reliability of Scales. Journal of Extension 37, 1–5.
 
41.
Sunjka, BP and Jacob, U 2013. Significant causes and effects of project delays in the Niger delta region, Nigeria. SAIIE25 Proceedings, Stellenbosch, South Africa, July, 9th – 11th, 1–14.
 
42.
Serani, N, Dusso, T and Wodaje, B 2020. The Causes and Effects of Delay of Building Construction in Ethiopia, Southern Nation Nationalities of People Region in Gurage Zone (Case of Wolkite Town). Civil and Environmental Research 12, 12–21.
 
43.
Sweis, G, Sweis, R, Abu Hammad, A and Shboul, A 2008. Delays in Construction Projects: The Case of Jordan. International Journal of Project Management 26 (6): 665–74.
 
44.
Tafazzoli, M and Shrestha, PP 2017. Investigating Causes of Delay in U.S. Construction Projects, 53rd ASC Annual International Conference Proceedings, Associated Schools of Construction, April 5-8, 611–21.
 
45.
Ullah, K, Khan, MS, Lakhiar, MT, Vighio, AA and Sohu, S 2018. Ranking of Effects of Construction Delay: Evidence from Malaysian Building Projects. Journal of Applied Engineering Sciences 8, 79–84.
 
46.
Yogita, G and Attarde, P 2015. Assessment Of Significant Causes And Effects Of Delays On The Projects Completion Period. InternInternational Journal of Modern Trends in Engineering and Research 0 2, 88-93.
 
47.
Costello, AB and Osborne, J (2005). Best practices in exploratory factor analysis: four recommendations for getting the most from your analysis, Practical Assessment, Research, and Evaluation 10, 1-9.
 
eISSN:2450-8594
ISSN:2080-5187
Journals System - logo
Scroll to top